Installation

Preparing the Machine

Gas Models Only

  1. Park the machine on a level surface.

  2. Disengage the blade-control switch.

  3. Move the motion-control levers outward to the NEUTRAL-LOCK position.

  4. Shut off the engine and remove the key.

  5. Wait for all moving parts to stop.

  6. Allow machine components to cool.

Electric Models Only

  1. Park the machine on a level surface.

  2. Disengage the blade-control switch.

  3. Move the motion-control levers outward to the NEUTRAL position.

  4. Engage the parking brake.

  5. Shut off the machine and remove the key.

  6. Wait for all moving parts to stop.

  7. Allow machine components to cool.

  8. Remove the battery packs from the machine.

Installing the Floormat

Parts needed for this procedure:

Floormat1
Plastic plug8

Secure the floormat to the platform using the plastic plugs.

g467787
g467788